UPDATED JANUARY 8, 2026

How Long Is the PJM Interconnection Queue Wait Time? (2026 Tracker)

The PJM interconnection queue averages 36-48 months for datacenter projects over 100MW as of January 2026. The queue backlog exceeds 250GW with 2,600+ active projects. PJM is 33% slower than ERCOT but offers more predictable timelines.

  • Large Projects (>100MW): 36-48 months
  • Medium Projects (50-100MW): 30-42 months
  • Small Projects (<50MW): 24-36 months
  • Queue Backlog: 250GW+ (2,600+ projects)

Access the Live TTPS Tracker

Our Time-to-Power Score tracker is completely free. View interconnection queue data, wait time estimates, and regional comparisons.

How Does PJM Queue Compare to ERCOT?

MetricPJMERCOTAdvantage
Average Wait Time36-48 months24-36 monthsERCOT (33% faster)
Queue Backlog250GW+205GWSimilar
Timeline PredictabilityHighMediumPJM
Curtailment RiskLow (capacity market)Medium (energy-only)PJM
Power Cost$0.06-0.09/kWh$0.03-0.05/kWhERCOT
Study ProcessCluster (annual windows)Serial + Fast TrackERCOT (flexibility)

Site Selection Insight

Choose PJM for enterprise customers requiring ultra-low latency to Northern Virginia, NYC, or Philadelphia. Choose ERCOT for AI training where power cost matters more than location and 6-12 month faster energization justifies higher operational risk.

Which PJM Zones Have Shortest Queue Times?

ZoneLocationEst. Wait TimeCapacity StatusDatacenter Activity
DominionNorthern Virginia42-54 monthsConstrainedHighest (AWS, Azure, Google)
PSEGNew Jersey36-48 monthsModerateHigh
ComEdChicago, IL30-40 monthsAvailableGrowing
PECOPhiladelphia, PA30-40 monthsAvailableModerate
BGEBaltimore, MD32-42 monthsAvailableGrowing
AEPOhio/WV28-38 monthsAvailableEmerging

What Are PJM Interconnection Study Costs?

$50-100K

Feasibility Study

Initial grid impact assessment

$100-300K

System Impact Study

Detailed reliability analysis

$200-500K

Facilities Study

Engineering & cost estimates

Network Upgrade Cost Warning

Beyond study costs, PJM may require network upgrades totaling $10-50M+ for large datacenter projects. These costs are often shared among clustered projects but represent significant capital at risk if project doesn't proceed.

How Can You Speed Up PJM Interconnection?

Site Selection Strategies

  • 1.Target zones with available capacity (ComEd, PECO, AEP)
  • 2.Locate near recently upgraded substations
  • 3.Consider behind-the-meter generation to reduce load
  • 4.Avoid constrained corridors (NoVA, NJ coastal)

M&A & Development Strategies

  • 1.Acquire queue positions from stalled projects
  • 2.Partner with existing generators for co-location
  • 3.Use cluster study approach for cost sharing
  • 4.Engage PJM-experienced consultants early

Our Methodology

This PJM queue analysis is based on:

  • Data sources: PJM Queue Management system, OASIS data, utility filings
  • Project tracking: 2,600+ active queue positions monitored weekly
  • Completion analysis: 500+ projects that reached Commercial Operation Date (COD)
  • Index integration: Time-to-Power Score (TTPS) for 40+ markets
  • Last updated: January 8, 2026

Limitations: Queue times vary by project size, location, and required upgrades. Actual timelines may differ from estimates. Consult PJM directly for project-specific guidance.

Frequently Asked Questions

How long is the PJM interconnection queue wait time?

The PJM interconnection queue averages 36-48 months for datacenter projects over 100MW as of January 2026. Smaller projects (<50MW) may complete in 24-36 months. The queue backlog exceeds 250GW with 2,600+ active projects.

Which PJM zones have shortest queue times?

ComEd (Chicago), PECO (Philadelphia), and BGE (Baltimore) zones have relatively shorter queue times (30-40 months) due to stronger grid infrastructure. Northern Virginia (Dominion zone) has the longest waits (42-54 months) due to datacenter concentration.

What is PJM's new cluster study process?

PJM's cluster study process (effective 2023) groups projects in annual windows rather than serial first-come-first-served. This aims to reduce study time from 4+ years to 2-3 years by studying similar projects together.

Grid & Power Strategy

Explore More

Related Tools

FREE TOOL

TTPS (Time-to-Power Score)

Interconnection queue wait time analysis

Open Tool
FREE TOOL

CSS (Curtailment Stress Score)

Real-time grid congestion and curtailment risk by zone

Open Tool
PRO TOOL

Capacity Auction Tracker

PJM/ERCOT capacity auction price analysis

Try Pro Tool

Track Your PJM Queue Position

Get real-time Time-to-Power Scores across PJM zones and compare to other markets.

Access TTPS Tracker →