GRID INFRASTRUCTURE

Datacenter Interconnection 101

Summary12 Data Sources

How long does grid interconnection take for datacenters?

Grid interconnection timelines vary dramatically by ISO: ERCOT averages 4-7 years with 205 GW in queue, PJM 3-5 years with 250+ GW backlog. The process involves application, study phases (feasibility, system impact, facilities), and construction. Costs range from $500K to $50M+ depending on required upgrades. Strategies to accelerate include site selection near substations, acquiring queue positions, and behind-the-meter generation.

Key Data Points

  • ERCOT Queue: 205 GW (4-7 year timeline)
  • PJM Queue: 260 GW (3-5 year timeline)
  • Study Cost: $135K - $950K total
  • Construction Cost: $2.5M - $80M+
  • Study Phases: Feasibility (3-6mo), System Impact (6-18mo), Facilities (3-6mo)

Interconnection Process Overview

1

Application

Submit request, pay deposit, enter queue

2-4 weeks

2

Feasibility Study

Initial technical assessment

3-6 months

3

System Impact

Detailed grid modeling

6-18 months

4

Facilities Study

Engineering & cost estimates

3-6 months

5

Construction

Build required upgrades

12-36 months

Interconnection by ISO/Region

ISO/RegionQueue SizeAvg TimelineDepositStatus
ERCOT (Texas)205 GW4-7 years$100K+Severely congested
PJM (Mid-Atlantic)260 GW3-5 years$1M+Reform underway
CAISO (California)85 GW3-4 years$500K+High demand
MISO (Midwest)180 GW2-4 years$250K+Growing backlog
SPP (Great Plains)95 GW2-3 years$100K+Moderate
ISO-NE (New England)35 GW2-3 years$200K+Manageable

Queue data as of January 2026. Check TTPS Tracker for real-time updates.

Interconnection Cost Components

Study Costs

Application Deposit$10K - $100K
Feasibility Study$25K - $100K
System Impact Study$50K - $500K
Facilities Study$50K - $250K
Total Study Costs$135K - $950K

Construction Costs

Substation Upgrades$1M - $20M
Transmission Line$1M - $5M/mile
Network Upgrades$0 - $50M+
On-site Interconnection$500K - $5M
Total Construction$2.5M - $80M+

Strategies to Accelerate Interconnection

Site Selection

  • Choose sites near existing substations with capacity
  • Avoid areas with known transmission constraints
  • Consider sites with retiring generation (headroom)
  • Look for industrial sites with existing service

Queue Strategies

  • Acquire existing queue positions from other projects
  • Submit multiple applications at different sites
  • Apply for smaller initial capacity, expand later
  • Engage consultants with ISO relationships

Behind-the-Meter

  • On-site generation bypasses queue entirely
  • Natural gas can deploy in 18-24 months
  • Solar+storage in 12-18 months
  • Hybrid approach: BTM now, grid connection later

Utility Partnerships

  • Economic development agreements with utilities
  • Contribution-in-aid-of-construction (CIAC)
  • Utility-owned generation partnerships
  • Green tariff programs with priority treatment

Frequently Asked Questions

Can I buy an existing interconnection position?

Yes, queue positions can sometimes be acquired through project/site acquisitions or assignment agreements. Prices range from $10-50/kW depending on position, location, and time remaining. This is increasingly common in congested markets like ERCOT and PJM.

What are network upgrade costs and who pays?

Network upgrades are grid improvements needed to accommodate your load/generation. Costs can range from $0 (if existing capacity) to $50M+ (new transmission). Depending on ISO rules, you may pay upfront and receive partial refunds over time, or costs may be socialized.

How is FERC Order 2023 changing interconnection?

FERC Order 2023 (effective 2024) reforms the interconnection process: cluster studies instead of serial, stricter readiness requirements, financial commitment deposits, and faster timelines. Impact varies by ISO implementation.

What happens if my project is delayed?

Most ISOs allow limited delays with additional deposits. Extended delays may result in queue position loss and forfeited deposits. Milestone requirements are becoming stricter under FERC Order 2023 reforms.

Check Time-to-Power Scores

Our TTPS tracker analyzes interconnection queue data to score sites by expected time to power.

Open TTPS Tracker →

Explore More

Related Tools

FREE TOOL

TTPS (Time-to-Power Score)

Interconnection queue wait time analysis

Open Tool
FREE TOOL

CSS (Curtailment Stress Score)

Real-time grid congestion and curtailment risk by zone

Open Tool
FREE TOOL

Site Readiness Scores

Project readiness assessments across permitting, interconnection, construction

Open Tool